Central work nears end
The 100 block of Central Avenue is set
to be open by Friday afternoon, city manager Chuck Stearns
reports.
Paving of the 100 block was expected
for Tuesday and Wednesday this week. Construction crews are set to
stripe parking lanes, install signs, benches and trash cans and
cleanup on Thursday and Friday.
Last week crews finished sidewalks and
curbs. The concrete machine for the gutter pans did not work well
and the pans were poured by hand on Saturday.
Schellinger Construction is 82 percent
complete with 66 percent or work time elapsed.
The work is scheduled to be completed
on June 13 with early completion on May 27.