Debris hampers river cleanup
The cleanup of the Whitefish River is
behind schedule and could cause work to spill into 2013.
“We haven’t gotten as far as we
anticipated,” said Jennifer Chergo with the U.S. Environmental
Protection Agency.
The EPA began work to clean up
contaminated sediment in the river in late July. Crews are using a
wet dredging system that sucks up the soil and pumps it up river to
be cleaned. A few issues have made work slower than expected.
“There’s been mechanical problems with
the barge and a lot more debris in the river than we expected,”
Chergo said. “That’s slowed us down a little bit.”
The mechanical issues with the barge
have been repaired as needed, Chergo said.
However, the dredging system, which
works like a large vacuum, has been sucking up more than expected.
Large debris such as trees and rocks are removed from the river,
but other smaller items often become stuck in the vacuum and need
to be dislodged. Crews have found a number of items including tin
cans, fuel filters and even Ford Model T tires.
Cleanup work began at the Second Street
bridge and was expected to reach Baker Avenue before stopping work
in November for the winter. However, now it’s expected crews will
only make it from their starting point to near Mountain View
Manor.
The slower progress means the duration
of work will likely lengthen.
“We want people to know that we won’t
make it down to Baker and cleanup will likely roll into 2013,”
Chergo said. “This is important because we have to close the river
to do the work.”
The cleanup project was initiated after
EPA received a report in 2007 of an apparent sheen at several
locations on the Whitefish River. EPA investigated and discovered
petroleum products contaminating river sediments at several sites
along the river. EPA ordered BNSF to clean up petroleum
contamination in the river and restore the river.
The project is in its third phase.
Cleanup has been completed on a 500-foot stretch of the river below
the BNSF roundhouse and refueling facility and in the river’s upper
reach.
Crews are still expected to work into
November and then resume operations in March or April 2012. With
about 5,000 feet of river to be cleaned work will eventually make
its way downriver to JP Road.