Park construction costs detailed
Here’s a look at what some of the reconstruction contracts on the Sun Road have cost, according to figures provided on the Federal Highway Administration Web site:
• Additional parking at the Apgar Transit Center (not completed): $617,945
• Avalanche to the West Side Tunnel: $5.31 million
• Logan Pass to Siyeh Bend: $10.831 million
• Big Bend to Logan Pass: $14.987 million
• Rehabilitate the West Entrance Station: $809,556
• Rehabilitate the the St. Mary Visitor Center: $2.279 million
• Crystal Point to Haystack Creek, $9.990 million
• West Side Tunnel to Haystack Creek: $12.2 million.
To view the all the items currently on the list, visit online at www.wfl.fhwa.dot.gov/contracting/construction/idiq/gtsr.htm.